APPLICATION CHECKSHEET FOR LEAD
CONTRACTOR
State Form 50745 (R3 / 10-07)
INDIANA STATE DEPARTMENT OF HEALTH
INSTRUCTIONS:
1.
INDIANA STATE DEPARTMENT OF HEALTH
Lead-based Paint Program
2 N Meridian St, 5 J
Indianapolis, IN 46204
Phone: (317) 233-1250
Do not return this sheet with application.
http://www.in.gov/isdh/programs/lead/
2. This checklist is used by ISDH to review your Form 48739
“Application for Lead Contractor License” and is provided only to
assist you in compiling a complete Standard Operating Procedures
manual for submittal with the lead contractor license application.
FOR OFFICE USE ONLY BY REVIEWER
Company name:
Applicant name:
Designated Representative name:
Reviewed by:
Date reviewed:
TYPE OF LICENSE
NEW LICENSE
LICENSE RENEWAL - Expiration date: ______/______/______
STATUS
APPROVED
DENIED PENDING ADDITIONAL INFORMATION
PART A: CHECKLIST - GENERAL INFORMATION
► Has the contractor satisfied the following general requirements?
YES
NO
RULE
REQUIREMENT
General and personal information provided
326 IAC 23-2-4(b)(4)
If no, provide the following:___________________________________________________________
326 IAC 23-2-4(b)(12)
Proof of financial responsibility attached
Verified: ______________________________________________________________________
326 IAC 23-2-4(b)(1)
Indiana Project Supervisor License
Submitted copy of current Indiana lead-based paint Project Supervisor license
326 IAC 23-2(4)(b)(7)
Standard Operating Procedures (SOP) Manual
Copy of contractor's written standard operating procedures for the following regulatory programs:
326 IAC 1-1; 326 IAC 23-1; 326 IAC 23-4-11; 29 CFR 1926.62; and 29 CFR 1910.134
NOTE: SOP manual should include detailed, specific written procedures for contractor’s compliance
with Indiana’s lead laws. This includes notification, work practice, and licensing requirements.
PART B: CHECKLIST - 326 IAC 23-4
► Has the contractor satisfied the following requirements to comply with 326 IAC 23-4?
YES
NO
RULE
REQUIREMENT
Applicability of Rule
NOTE:
326 IAC 23-4-1(a) & (b)
Any person or company performing lead-based paint activities shall comply with the appropriate work
practices.
A political subdivision or a state agency may not accept a bid for a lead-based paint activities project.
Page 1 of 3
American LegalNet, Inc.
www.FormsWorkflow.com
Application Checksheet For Lead Contractor
10/07
INDIANA STATE DEPARTMENT OF HEALTH
LEAD-BASED PAINT PROGRAM
State Form 50745 (R3 / 10-07)
PART B: CHECKLIST - 326 IAC 23-4 (continued)
► Has the contractor satisfied the following requirements to comply with 326 IAC 23-4?
YES
NO
RULE
REQUIREMENT
326 IAC 23-1-3, 7, & 63
Definitions (adequate quality control, child-occupied facility, target housing)
326 IAC 23-4-6
Indiana notification requirements/contents/schedule/form
Lead abatement procedures - interior
326 IAC 23-4-7(1) - (8)
Post warning signs
Wall to wall carpeting
Wrapped with six (6) mil polyethylene
Area shall be sealed from non-work areas
After sealing off the work area, floors shall be covered,
Forced-air heating and air conditioning systems shall be shut down,
Alternative entrances and egresses that are located outside of the work area,
Work area shall be cleaned with HEPA vacuum
Lead abatement procedures - exterior
326 IAC 23-4-8(1) - (3)
Uncontained water, and abrasive blasting
Before abating lead paint using wet methods on exterior work areas, the following site
preparation procedures shall be used: 23-4-8(2)(A-E)
Before beginning to abate lead paint using dry methods on exterior work areas, the following
site preparation procedures shall be used: 23-4-8(3)(A-D)
326 IAC 23-4-15
Notification fees
326 IAC 23-4-9(1) - (6)
Post-abatement clearance procedures
Lead-based paint sampling procedures
Clearance sampling under section 9 of this rule shall be conducted as follows:
326 IAC 23-4-10(1) - (4)
Dwelling will be selected for the random sample.
Dwellings are selected for dust sampling.
A licensed supervisor or project designer shall prepare a report; the report shall include (A)-(F).
PART C: CHECKLIST - 326 IAC 23-4-11; 29 CFR 1926.62 and 1910.134
► Has the contractor satisfied the following requirements to comply with 326 IAC 23-4-11?
YES
NO
RULE
REQUIREMENT
326 IAC 23-4-11(1) - (5)
Lead-based paint abatement disposal procedures
Follow these procedures when disposing of lead- based paint waste- (1)-(5)
Construction Standard:
29 CFR 1926.62
29 CFR 1910.134
Permissible exposure limit
Regulated areas
Exposure monitoring
Engineering controls & work practices
Respiratory protection
Protective clothing
Hazard communications to employees
Medical surveillance
Respiratory Protection Standards
Page 2 of 3
American LegalNet, Inc.
www.FormsWorkflow.com
Application Checksheet For Lead Contractor
10/07
INDIANA STATE DEPARTMENT OF HEALTH
LEAD-BASED PAINT PROGRAM
State Form 50745 (R3 / 10-07)
PART D: CHECKLIST - 326 IAC 23-2-4(b)
► Has the contractor satisfied the following requirements to comply with 326 IAC 23-2-4(b)?
YES
NO
RULE
REQUIREMENT
326 IAC 23-2-4(b)(4)
Competency
Demonstrated competency in the field of lead project implementation and has read and understands
326 IAC 23 and 40 CFR 745.
326 IAC 23-2-4(b)(6)
Prior Contracts
A complete list of prior contracts for the previous 36 months for lead projects including names,
addresses & telephone numbers of persons for whom projects were performed
326 IAC 23-2-4(b)(8)
Terminated Lead Projects
A description of any lead-based paint projects which were prematurely terminated or not completed,
including circumstances surrounding termination
326 IAC 23-2-4(b)(9)
Contractual Penalties
A list of any contractual penalties related to lead-based paint activities that contractor has paid for
noncompliance with contract specifications
326 IAC 23-2-4(b)(10)
Citations/Violations/Findings
Copies of any and all citations, notices of violation, or findings of violation levied against the
contractor for violations of regulations pertaining to lead abatement and a description of how the
allegations were resolved
326 IAC 23-2-4(b)(11)
Legal Actions/Claims
A description detailing all legal proceedings, lawsuits or claims levied against the contractor or any of
his/her past or present employees while employed by the contractor, for lead-based paint related
activities
PART E: CHECKLIST - OTHER
► Are the following items included with contractor application?
YES
NO
RULE
REQUIREMENT
326 IAC 23-2-4(b)(1)
White colored lead signature cards signed and attached
326 IAC 23-2-4(e)
Two 1-½ inch by 1-½ inch recent color photographs of applicant attached
326 IAC 23-2-4(b)(2)
Application signed
326 IAC 23-2-8
Application fee of $150 submitted with application
PART F: REVIEWER'S COMMENTS
Page 3 of 3